Nobody in Orlando calls it the Permitting Services Division. They call it the building department, or “the city”, as in “the city failed my framing”. Whatever you call it, if you build, remodel, re-roof or sell a house inside the City of Orlando, you will deal with it, and the experience goes a lot better when you know how it works before you need it.
This guide is the plain version: where the office is and when it is open, which number to ring for what, how a permit moves from application to final, how to book an inspection without waiting on hold, and what to do when one fails. Everything about the city’s own rules, fees and numbers comes from the city’s website, and we have dated it so you know how fresh it is. The charts come from the city’s permit records, the same records we work from every day, and they update themselves.
Who the Orlando building department actually is
Officially, the building department is the Permitting Services Division, which sits inside the city’s Economic Development Department. It handles residential and commercial permitting, and it also collects the city’s business taxes, which is why the same counter deals with a roofer’s permit and a new café’s business tax receipt.
Inside it, the work splits roughly three ways, and knowing which one you need saves a transfer or two:
- Permitting and plan review. Applications, plan uploads, review comments, fees and the permit itself.
- Inspections. The inspectors who come out to the job, plus the scheduling systems. Inspections have their own phone line and their own text service.
- Business tax. The business tax receipt every business operating inside the city limits needs. Not a building matter, but the same division, which surprises people.
Fire permits, right-of-way work on city streets, tree removal and zoning questions all touch construction too, and some of them involve other city departments. If your question is about one of those, the permitting line can usually tell you where to go.
Where it is, when it is open and who to call
The division is on the first floor of Orlando City Hall, 400 South Orange Avenue, Orlando, FL 32801, downtown. City Hall is open Monday to Friday, 8 a.m. to 5 p.m., and closed on the holidays the city observes. Much of what used to need a visit is now done online, so check whether you need to go in at all before you pay for downtown parking.
- Permits
407.246.2271
The main Permitting Services line. Also the help line for ProjectDox, the city’s plan upload system.
- Email
digitalpermits@orlando.gov
Applications, changes after a permit is issued, and requests for a copy of a Certificate of Occupancy or Completion.
- Book an inspection by phone
407.246.4444
The automated inspection line. Press 1 for construction inspections, permit or license information.
- Book an inspection by text
866.205.3881
Text INSPECTION to be walked through it, or SCHEDULE with your permit number, inspection code and date.
- Inspection questions
407.246.3254
The number the city gives for questions about phone and text scheduling.
- City Hall
407.246.2121
The main switchboard, Monday to Friday, 8 a.m. to 5 p.m.
A few more addresses are worth knowing if they apply to you. Expired permit renewals go to permitrenewals@orlando.gov. Virtual inspections are arranged through remoteinsp@orlando.gov. Private provider paperwork goes to privateprovider@orlando.gov. The city also lists an emergency permitting number, 407.246.3420, on some of its pages.
One tip that sounds obvious and is not: always have the permit number ready, in full, before you call or email. Nearly every system the city uses, from the phone tree to the text service, starts by asking for it, and it is the one thing that cannot match the wrong job.
First check: is the address in the City of Orlando?
Before you ring anyone, make sure the property is actually inside the city limits. This catches out more people than anything else on this page. An “Orlando, FL” mailing address can just as easily be in unincorporated Orange County, or in Winter Park, Maitland, Belle Isle or Edgewood, each of which has its own building department. How to tell which one you are dealing with, and how the county’s Fast Track system works, is in Orange County permit search.
How a permit moves through the department
The State of Florida requires a permit for most building work, including a lot of small jobs that people assume are exempt. The city’s own summary of the process runs to nine steps. Here it is, squeezed into the stages that matter.
Apply
Send the application
Fill in the right form from the city’s Permitting Forms page. Allow two business days for processing.
Upload
Plans go into ProjectDox
The applicant gets an emailed link to ProjectDox, the city’s digital plan review system, and uploads the plans.
Review
Reviewers check the plans
Track progress and review completion dates in the city’s Permit Lookup.
Pay
Fees, then the permit
Once every review is approved, the city emails payment instructions. Pay through Permit Lookup.
Build
Post plans and the permit
Download the approved plans, print them to scale and post them on site, with the permit, before work starts.
Inspect
Inspections, then final
Book each inspection as the job reaches it. Pass the last one and the permit is final.
A few details from the city’s guide that people miss:
- Commercial jobs pay a deposit first. After a commercial application is processed, the city emails an invoice for a non-refundable 25% plan review deposit, and only then sends the ProjectDox link.
- Fees come at the end of review, not the start. The city sends payment instructions after all reviews are approved and the contractor’s details are attached to the permit. If you are waiting on an invoice, check that the contractor information is complete.
- Changes after issue go by email. To change approved plans, answer an inspector’s corrections or clear a document hold, email a short narrative to digitalpermits@orlando.gov asking them to reopen the portal, and say why.
- Your Certificate of Occupancy or Completion can be requested from the same address. Put the permit number in the subject line.
Throughout all of this, the city’s Permit Lookup is the dashboard. It shows the permit’s status, the review completion dates, related permits, fees due and inspection results. It is the same lookup homeowners use to check a contractor, which we walk through in City of Orlando permit search.
The Notice of Commencement
If a job’s contract price is over $5,000, the city needs a recorded Notice of Commencement before you can book inspections. This trips up a lot of first-time owner-builders and some contractors new to Florida, because it is filed with the county, not the city.
- Record the Notice of Commencement with the Orange County Comptroller’s office. It can be done online.
- Send the city a copy of the recorded notice, through the upload the city provides for it.
- Post a certified copy of the recorded notice on the job site, where the inspector can see it.
The notice exists to protect the owner and the people who supply labor and materials to the job, and Florida’s construction lien rules lean on it. If you skip it, the practical result in Orlando is simple: your first inspection does not happen.
What the department handles in a year
It helps to know what the department is busy with, because it shapes how fast anything moves. This is how the residential building permits the city processed over the last 12 full months break down by kind of work. Watch how much of it is re-roofing, which is what you would expect in a city with a lot of houses built in the same few decades and a hurricane season every summer.
City of Orlando permit records, Nov 2025 to Oct 2026. Electrical, plumbing and mechanical permits are separate and not counted here.
And this is the monthly flow for one kind of permit, re-roofing, so you can see how the workload rises and falls. Busy months mean longer queues for reviews and inspections, so a job that needs a permit in a peak month needs more slack in its schedule.
See the numbers
| Month | Permits |
|---|---|
| Nov 2025 | 182 |
| Dec 2025 | 259 |
| Jan 2026 | 210 |
| Feb 2026 | 192 |
| Mar 2026 | 261 |
| Apr 2026 | 263 |
| May 2026 | 217 |
| Jun 2026 | 209 |
| Jul 2026 | 228 |
| Aug 2026 | 168 |
| Sep 2026 | 165 |
| Oct 2026 | 181 |
City of Orlando permit records, Nov 2025 to Oct 2026, counted by the month the city processed the application.
Inspections, in short
Every issued permit needs at least one inspection, and most need several. Inspections happen on weekdays between 7 a.m. and 3:30 p.m., and you book them yourself: in Permit Lookup, by text on 866.205.3881, or on the automated phone line, 407.246.4444 (6 a.m. is the latest you can book for the same day). Each booking needs the permit number and an inspection code.
Inspections have enough moving parts to need their own guide, so they have one. Our guide to City of Orlando inspections lists every inspection code for home projects, the usual order for pools and new homes, what has to be on site, the status messages that block a booking, what a failed inspection costs, and the overtime and virtual inspection options.
How long permits take, from filing to final
This is the question everyone asks and the city cannot answer in general, because it depends on the job. But the city’s permit records hold both dates for every permit, so we can show what actually happened. This chart times every permit on our six lists that passed final inspection in the last 12 full months, from the day the city processed the application to the day of the final inspection.
See the numbers
| Permit type | Typical days | Middle half (days) | Permits counted |
|---|---|---|---|
| AC replacements | 26 | 13 to 63 | 1,054 |
| Roofs | 30 | 14 to 86 | 2,436 |
| Fences | 63 | 35 to 124 | 322 |
| Remodels | 134 | 70 to 237 | 411 |
| Pools | 245 | 181 to 343 | 248 |
| New homes | 280 | 196 to 427 | 926 |
City of Orlando permit records, permits finaled Nov 2025 to Oct 2026, timed from the date the city processed the application.
Read it as what happened, not as a promise. The clock includes everything: the review, the wait for fees, the actual building, weather, supply delays and the time it takes to book each inspection. A re-roof or an AC change-out is a short job, so most of those permits close within weeks. A pool or a new house is months of work, and the permit stays open for all of it. Remodels sit in between and vary the most, because “remodel” covers everything from a bathroom to half a house.
The middle-half figure is the useful one for planning. It is the range that covers the typical half of jobs, leaving out the fastest quarter and the slowest quarter. If your job is running well past the top of that range, something is probably stuck, and it is worth checking Permit Lookup for an unpaid fee, a hold or an inspection that never got booked.
Expired permits and the six-month rule
The city puts it plainly: if a permit is open for six months without an inspection, it expires. That is the rule that bites on slow jobs, owner-builder projects that stall, and jobs where the contractor left before the end.
An expired permit is not just a paperwork problem. The city warns that it can cause delays with future inspections, title searches and the sale of the property. The fix is a renewal:
- Check the permit’s status in Permit Lookup to confirm it has expired.
- Fill in the city’s online renewal request.
- A permit technician reviews it and lets you know within three business days whether the permit can be renewed or needs a replacement permit.
- If it is approved, you pay the minimum permit fee or 25% of the original permit fee, whichever is greater, up to $1,000, within six months of the expiration.
There is also a separate request for a permit extension if you can see the deadline coming. Asking before the permit expires is always easier than renewing after.
Using a private provider instead
Florida law lets owners use a private provider for plan review, inspections or both, instead of the city’s own staff. Private providers have to be architects, engineers or hold a specific state certificate, and they use licensed plan reviewers and inspectors. Their work is limited to building code compliance: they cannot sign off fire safety, site work, zoning, floodplain or the other reviews the city still does itself.
The city cuts part of its fee when you use one. For homes with one or two units, the city lists a 75% reduction to the Florida Building Code fee item when the private provider does both plan review and inspections, and 50% for inspections only. The reduction applies only to that one fee item, not to impact fees, the technology fee or the other charges on the permit. For the plan review reduction, the Notice to Building Official has to go in with the permit application; for inspections only, it has to reach the city before the first inspection.
Whether it is worth it is a business decision. The provider charges for their time, so the saving on the city fee is only part of the sum. For a builder with a steady pipeline, more control over review and inspection timing can be worth paying for. For a single home project, the sums are less likely to work.
Closing out: why the final inspection matters
Once the last inspection passes, the permit is final. The city is blunt about why this matters: if you do not close out a permit, it can cause problems later when you try to sell the property. Open permits show up in buyers’ searches, and a permit left open for years raises the obvious question of whether the work was ever finished properly.
For homeowners, the habit is simple: before you make the last payment to a contractor, check Permit Lookup and make sure the status says final. For contractors, closing out is part of the job, and a short list of permits that never got their final inspection is a reputation problem waiting to happen.
In the city’s published records, a permit that passed its final inspection gets a status of Finaled and a final date, and every application the department processes shows up there too, updated daily. That makes the department’s paperwork one of the best lists in the city of homes having money spent on them right now. How local trades use it is in building permit leads, and we send each morning’s new permits for six kinds of home project to subscribers, with the owner on record added.