Inspections are where a permit stops being paperwork. The plans are approved, the fees are paid, the work has started, and now someone from the city has to come and look at it, usually more than once. Most of the stress around City of Orlando inspections comes from three things: not knowing which inspections a job needs, not knowing what the codes mean, and getting stopped by a permit status nobody explained.

This guide deals with all three. It lists the city’s inspection codes for home projects, shows the usual order for pools, new homes and the common smaller jobs, explains every status message that can block a booking, and finishes with what the final inspection means. For the office itself, its hours and phone numbers, see our guide to the Orlando building department.

City inspections are not home inspections

A quick clarification first, because the two get mixed up all the time.

  • A city inspection is done by the City of Orlando, or by a private provider standing in for it, on work done under a building permit. It checks that piece of work against the Florida Building Code at a specific stage. It is required, and the permit cannot close without it.
  • A home inspection is a private service a buyer hires before closing. The inspector looks at the whole house, not one job, and works for the buyer, not the city.

The two do meet. A buyer’s agent or home inspector will often look up the permit history, and a roof or addition that never passed its final city inspection is exactly the sort of thing that comes up. How to check that history is in our City of Orlando permit search guide. The rest of this page is about city inspections.

The inspection codes, and how to read them

Every inspection the city does has a three-digit code, and you need the right one to book. The city groups them by trade: building, electrical, mechanical, plumbing and gas, swimming pool, demolition, moving, engineering, fire and right-of-way.

Three things make the list easier to read than it first looks:

  • The trade matters as much as the number. The same number can mean different things in different trades. 200 is the electrical rough-in and also the plumbing rough gas. 199 is the electrical pre-power and also medical gas. When you book, you choose the permit first, so the system knows which trade you mean.
  • 600 is always a final. Building, electrical and engineering each have a 600. On a job with several permits, each one needs its own final.
  • The order of the building codes roughly follows the build. Footer, slab, columns, tie beam, walls, roof deck, dry-in, strapping, framing, insulation, stucco, then the finals. That is the order a typical Central Florida block house goes up.

The full list for home projects

These are the City of Orlando’s inspection codes for the four trades a house involves, exactly as the city lists them. The engineering, fire, right-of-way, demolition and moving codes are on the city’s Inspection Codes Guide; most home projects never need them, apart from the pool and new home inspections covered further down.

Building inspection codesCity of Orlando Inspection Codes Guide, November 2026. The city’s wording.
CodeInspection, as the city names it
100Footer
405Slab
310Vertical Cells/Columns
305Lintel/Tie Beam
315Masonry Wall Reinforcing
120Roof Decking
125Ext. Dry-In/In Progress
127Ext. Strapping/Wall Sheathing
130Framing
132Rated Assembly Fastening
135Above Ceiling
147Rated Assembly/Penetration
140Insulation
170Zoning Final
325Lath/Stucco
150Fire Final (BLD)
345Mobile Home Tie Down
340Pool Steel
342Pool Deck/Piping Pressure
343Pool Safety Check
600Final
Electrical inspection codesCity of Orlando Inspection Codes Guide, November 2026. The city’s wording.
CodeInspection, as the city names it
341Pool/Deck Bonding Insp.
350Temporary Service
351Tug Inspection
355Underground/Slab
200Rough-In
199Pre-Power
112Footer Steel & Grounding
Mechanical inspection codesCity of Orlando Inspection Codes Guide, November 2026. The city’s wording.
CodeInspection, as the city names it
202Framing/Fire Damper
205Kitchen Hood
370Pipe Pressure Test
375Refrigeration
377Light Test
378Performance Test and Balance
Plumbing and gas inspection codesCity of Orlando Inspection Codes Guide, November 2026. The city’s wording.
CodeInspection, as the city names it
380Underground Rough-In
390Sanitary
010Tub Set/Shower Pan
230Water Pipe
240Sewer
242Interceptor
200Rough-Gas
250Rain Leader
199Medical Gas

A few of the names are shorthand. “Dry-in” is the stage where the roof is weather-tight under its underlayment, before the finished roof covering goes on. “Lintel/tie beam” is the reinforced concrete beam that runs along the top of block walls. “Rated assembly” means a wall or ceiling built to a fire rating, and “penetration” is anything that passes through it, like a pipe or a duct. “Bonding” on a pool ties the metal parts together electrically so they sit at the same voltage. If you are not sure what a particular inspection is checking, the inspector’s comments after a result, or the permitting line, will tell you.

Which inspections your job will need

The honest answer is: whatever your permit says. When the city issues a permit, the inspections it needs are attached to it, and you can see them in Permit Lookup under “View Inspections”, which lists the inspections that are available to schedule. That list beats anything in a guide, including this one, because it is set for your job.

Still, it helps to know roughly what to expect before you start, so you can plan the work around it. The next three sections cover the projects our customers watch for: pools, new homes, and the smaller jobs.

Pools: the city’s own list

Pools are the one home project where the city spells out the whole set, across all the trades involved. This is the city’s list for a swimming pool, in the order it gives them.

City of Orlando swimming pool inspectionsFrom the city’s Inspection Codes Guide, in the city’s order. Your permit’s list in Permit Lookup is the authority.
CodeTradeInspection
435EngineeringErosion control / silt fence
112ElectricalPool steel grounding
340BuildingPool steel
355ElectricalUnderground
341ElectricalPool deck / bonding
342BuildingPool deck / piping pressure
100BuildingFooter
343ElectricalPool safety inspection
343BuildingPool safety inspection
600ElectricalFinal
600EngineeringFinal
170BuildingZoning final
600BuildingFinal

Three things stand out. First, the electrical inspections are woven all the way through, from grounding the steel before the shell is shot to the final; a pool is as much an electrical job as a concrete one. Second, there are two pool safety inspections, one building and one electrical. They follow from a Florida law on residential pool safety, which we explain, along with what it means for fence and enclosure companies, in how to get pool service customers. Third, there is a zoning final, because a pool has to sit where the zoning rules allow.

With that many sign-offs, it is no surprise that pools are among the slowest permits to close. The live chart further down shows how long.

New homes: the order a block house goes up

A new house carries a building permit plus its own electrical, plumbing and mechanical permits, each with its own inspections and its own final. On the building side, the city’s codes follow the order of construction. For a typical concrete block house, the building inspections usually run something like this:

Building inspections on a typical new block houseThe usual order, using the city’s codes. Not every house needs every one; your permit lists its own.
  1. 100 · 405

    Footer, then slab

    Before concrete goes into the footings and before the floor slab is poured.

  2. 310 · 305 · 315

    Block walls

    Reinforced cells and columns, the tie beam along the top, and the wall reinforcing.

  3. 120 · 125 · 127

    Roof and envelope

    Roof decking, the dry-in, then strapping and wall sheathing.

  4. 130 · 140

    Framing, insulation

    Once the trades have roughed in their work, then the insulation before walls close.

  5. 325

    Lath and stucco

    The lath, before the stucco goes on the outside walls.

  6. 170 · 600

    Finals

    Zoning final and building final, after each trade permit has passed its own final.

The trade inspections slot in around these. Plumbing underground and electrical underground come before the slab is poured, because once the concrete is down nobody is getting under it. The electrical, plumbing and mechanical rough-ins come before the framing inspection, with the walls still open. Pre-power comes before the utility energizes the house. The order on any particular house is set by the permits, so ask the builder or check View Inspections rather than relying on a general list.

Roofs, AC change-outs, fences and remodels

Smaller jobs have far fewer inspections, which is why they close so much faster.

What the smaller jobs usually involveGeneral guidance only. Your permit’s list in Permit Lookup is the authority.
  • Re-roof

    Deck, dry-in, final

    Usually the roof decking and dry-in stages, then the final. Re-roofs on single-family homes and duplexes can use a virtual inspection.

  • AC change-out

    Mainly the final

    A like-for-like replacement is a mechanical permit, and the main event is the final inspection of the new system.

  • Fence

    Final

    A residential fence permit usually comes down to a final, with zoning rules on height and placement in the background.

  • Remodel

    Depends on the walls

    Anything that opens walls brings framing, trade rough-ins and insulation back into play. A kitchen refit is not a bathroom move.

Window and door replacements and water heater replacements on single-family homes and duplexes can be inspected virtually too. How that works is in the section on overtime and virtual inspections below.

Booking, in short

Inspectors work 7 a.m. to 3:30 p.m., Monday to Friday. You can book three ways, and all three need the permit number and the code.

  • Online: in Permit Lookup, enter the permit number and choose “Schedule Inspection”.
  • Text: send INSPECTION to 866.205.3881 to be walked through it, or send SCHEDULE, the permit number, the code and the date in one message. The city’s example is SCHEDULE BLD2018-00000 100 8/3.
  • Phone: call 407.246.4444, press 1, then option 1 twice. The cut-off for a same-day inspection is 6 a.m. Keep the confirmation number.

For the office itself, its hours and its other numbers, see the building department guide.

Overtime and virtual inspections

Two options exist for when the normal weekday slots do not suit, and few people use them because few people know about them.

Inspection options outside the normal slotCity of Orlando, as published in November 2026.
overtime inspection, first four hours
$292
each extra overtime hour
$73
notice needed for overtime
48 hrs
notice for a virtual inspection (business hours)
24 hrs

Overtime inspections cover anything outside 7 a.m. to 3:30 p.m. on weekdays. The licensed contractor has to request one at least 48 hours ahead, and it depends on an inspector being available. If the city approves it, it sends payment instructions; the fee is $292 for the first four hours and $73 for each hour after. You then book it in Permit Lookup and write “Overtime Request”, with the date and time, in the comments. A morning overtime inspection you no longer need has to be cancelled before 3 p.m. the day before.

Virtual inspections are for certain single-family and duplex jobs: re-roofing, door and window replacements and water heater replacements. The inspector joins on Microsoft Teams and tells you where to point the camera. You need a phone or tablet with a camera, the Teams app and a decent connection on site, and the request has to go in at least 24 business hours ahead. For a roofer or a window company running several small jobs a week, that can save a lot of waiting around.

When the system will not let you book

This is the most frustrating moment in the whole process, and it nearly always has a simple cause. When the city’s system refuses a booking, the permit has a status that explains why. These are the ones the city lists, with what each means and what the city says to do.

Permit status messages that block an inspectionFrom the city’s Understanding Your Permit Status page, November 2026.
StatusWhat it meansWhat to do
Collect FeesFees are due on the permit.Pay them through Pay Fees in Permit Lookup, or call 407.246.2271.
Contractor LicenseA contractor, or updated license paperwork, is needed.Email digitalpermits@orlando.gov or call 407.246.2271.
Document HoldThe city is waiting for final documents or revisions.Upload what is asked for in ProjectDox.
Pending CommencementThe job is over $5,000 and the city has no recorded Notice of Commencement.Record one with the Orange County Comptroller and send the city a copy.
Under Review / Pre-Screen ReviewCity staff are still reviewing the plans.Wait for the review to finish.
Pending IssuanceAll reviews are approved and fees are paid.The permit is about to be issued. Check Permit Lookup if it seems slow.
Pending OccupancyThe job is waiting for its Certificate of Occupancy or Completion.Email digitalpermits@orlando.gov to move it to final.
ExpiredThe permit has expired.Send the city a renewal request.

Two of these catch people more than the rest. Pending Commencement appears on any job over $5,000 until the city has a copy of the recorded Notice of Commencement, which is filed with the Orange County Comptroller, not the city. And Contractor License appears when a contractor’s details are missing or out of date on the permit, which happens when a job changes hands.

How to pass the first time

A failed inspection costs a fee and a day or more. One that cannot go ahead at all costs the same and teaches you nothing. Most of what follows is common sense, but it is the common sense that gets skipped on a busy week.

  1. Have the paperwork on site and visible. The city asks for the approved plans and any revisions, the permit and inspection sign-off sheet, a copy of the recorded Notice of Commencement, and any engineering documents. The permit should be visible from the street.
  2. Book the right code for the stage you are actually at. If the work is not ready, move the inspection the day before rather than hoping. Same-day cancellations cost $50.
  3. Build to the approved plans. If something changed on site, the plans need to change too. Revisions go through the city’s portal before the inspection, not after the inspector spots the difference.
  4. Make it easy to get to. Unlocked gate, dog inside, someone home if the work is inside. Use the message to the inspector when you book to say how to get in.
  5. Do not cover anything up early. Anything that should be seen at this stage, under a slab, inside a wall or under a roof covering, has to stay visible until it has passed.
  6. Read the comments from last time. If this is a re-inspection, the inspector’s notes from the fail are in Permit Lookup. Fix every item on them, not just the obvious one.

Reading the result, and what a fail costs

Results and the inspector’s comments appear in Permit Lookup under “View Inspections”, and on the automated phone line under option 1 and then option 3. There are three outcomes that matter:

  • Approved. Move on to the next stage.
  • Partially approved. Some of it passed, some did not. The city treats this like a fail for booking purposes: it has to be rescheduled.
  • Failed. Fix the items in the comments, then pay the re-inspection fee in Permit Lookup and book again. The fee has to be paid before the system will take the new booking.

Keep an eye on the calendar as well. The city says a permit that goes six months without an inspection expires, and a run of fails followed by a stalled job is exactly how that happens. How to renew one, and what it costs, is in the building department guide.

How long the inspection stage lasts

Once a permit is issued, the clock that matters is the one running to the final inspection. This chart measures exactly that stage, from the day the city issued the permit to the day it passed final, for every permit on our six lists that finaled in the last 12 full months. It is the building and inspecting part of the job, with plan review left out.

How long Orlando home permits stay open after they are issuedTypical (median) number of days from permit issued to final inspection, for permits that passed final inspection in the last 12 full months. Half took less time, half took more.
  1. AC replacementsmiddle half: 10 to 57 days23
  2. Roofsmiddle half: 13 to 82 days27
  3. Fencesmiddle half: 15 to 73 days31
  4. Remodelsmiddle half: 36 to 171 days79
  5. Poolsmiddle half: 133 to 284 days188
  6. New homesmiddle half: 147 to 292 days191
See the numbers
Permit typeTypical daysMiddle half (days)Permits counted
AC replacements2310 to 571,054
Roofs2713 to 822,432
Fences3115 to 73321
Remodels7936 to 171411
Pools188133 to 284248
New homes191147 to 292926

City of Orlando permit records, permits finaled Nov 2025 to Oct 2026, timed from the date the city issued the permit.

The pattern follows the number of inspections. A re-roof or an AC change-out has one or two, so most close within weeks of the permit being issued. A pool or a new house has a dozen or more across several trades, so the permit stays open for months. Remodels vary most, because the inspections depend on how much of the house is opened up.

If you want the whole journey, from the application going in to the final, the building department guide has the same chart measured from filing.

Other inspections the city does

Two more kinds of inspection come up in Orlando searches, and neither is part of an ordinary home permit.

Milestone inspections for condominiums. Florida law (section 553.899 of the Florida Statutes) requires a structural milestone inspection for condominium and cooperative buildings three stories or taller. The city sends certified letters to the associations whose buildings are due, and the inspection has to be done by a Florida-licensed architect or engineer. The city reviews the Phase One report and, if it finds problems, asks for a Phase Two report. Single-family, two-family and three-family homes with three or fewer habitable stories are exempt.

Inspections after flooding. After Hurricane Ian in 2022, homes and businesses whose interiors flooded needed a city inspection of the electrical before Orlando Utilities Commission would restore power. The city set up a request process and waived the related permit and inspection fees. Inspectors left a blue sticker on the meter when the electrical was safe, which told OUC it could turn the power back on. If a future storm floods your home, ask the permitting line whether the same process applies.

Private providers. Florida also lets owners use a private provider for building code inspections instead of city staff. The provider has to register with the city and file a Notice to Building Official before the first inspection, and the city reduces part of the permit fee. Fire, zoning, engineering and the other non-building reviews stay with the city.

The final inspection, and why it matters to other trades

When the last final passes, the permit is closed. In the city’s published records it gets the status Finaled and a final date. For the owner, that is the end of the job. For a lot of other businesses, it is the start of one.

  • A pool that passes final has an owner who now needs weekly service, and often a fence, an enclosure or landscaping. See how to get pool service customers.
  • A new house that passes final is about to get its first owners, with a bare yard and no regular services.
  • A remodel or a new roof that passes final marks a house that has just had money spent on it and will soon want the next thing.

That final date is public, and it is what our “just finished” leads are built on. Every morning we pick up the homes whose permits just passed final, and the ones that just filed, for six kinds of home project, and email them to subscribers with the owner on record. More on how that works in building permit leads.